Roads & HighwaysIPM · Central Project#618665

4L of Sagar - Mohari from Km.8 to Km.50 Pkg-I

Ministry of Road Transport & HighwaysMadhya Pradesh
Revised Cost: ₹660 CrUtilization: 68.8%

Original Cost

₹791 Cr

Baseline estimate

On budget

Revised Cost

₹660 Cr

Latest approved cost

Expenditure

₹455 Cr

Spent to date

Utilization

68.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹206 Cr

Budget left

Budget Utilization

68.8%
0%25%50%75%100%

Spent

₹455 Cr

Remaining

₹206 Cr

Total

₹660 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

05/04/2024

Revised Completion

07/06/2026

Completed

Project Details

Project Code618665
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMadhya Pradesh
Data Month2026-05

Financial Summary

Original Cost₹791 Cr
Revised Cost₹660 Cr
Expenditure₹455 Cr
Original End Date05/04/2024
Revised Date07/06/2026

Project Intelligence

Project is within original budget of ₹791 Cr — no cost escalation recorded.

Expenditure stands at ₹455 Cr, which is 68.8% of the revised project cost.

Remaining budget: ₹206 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Sagar - Mohari from Km.8 to Km.50 Pkg-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹791.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Sagar - Mohari from Km.8 to Km.50 Pkg-I"?
4L of Sagar - Mohari from Km.8 to Km.50 Pkg-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹791 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹791 Cr and has been revised to ₹660 Cr — a cost overrun of -16.5%. Expenditure to date: ₹455 Cr (68.8% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L of Sagar - Mohari from Km.8 to Km.50 Pkg-I is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618665. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Sagar - Mohari from Km.8 to Km.50 Pkg-I is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.