Roads & HighwaysIPM · Central Project#618836

4L of Ratnagiri - Kolhapur section from km 67.140 to km 112.340 of NH-166 Pkg II

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹1798 CrUtilization: 69.0%

Original Cost

₹1985 Cr

Baseline estimate

On budget

Revised Cost

₹1798 Cr

Latest approved cost

Expenditure

₹1240 Cr

Spent to date

Utilization

69.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹558 Cr

Budget left

Budget Utilization

69.0%
0%25%50%75%100%

Spent

₹1240 Cr

Remaining

₹558 Cr

Total

₹1798 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/05/2025

Revised Completion

12/01/2027

Completed

Project Details

Project Code618836
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹1985 Cr
Revised Cost₹1798 Cr
Expenditure₹1240 Cr
Original End Date24/05/2025
Revised Date12/01/2027

Project Intelligence

Project is within original budget of ₹1985 Cr — no cost escalation recorded.

Expenditure stands at ₹1240 Cr, which is 69.0% of the revised project cost.

Remaining budget: ₹558 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Ratnagiri - Kolhapur section from km 67.140 to km 112.340 of NH-166 Pkg II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1985.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Ratnagiri - Kolhapur section from km 67.140 to km 112.340 of NH-166 Pkg I"?
4L of Ratnagiri - Kolhapur section from km 67.140 to km 112.340 of NH-166 Pkg II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹1985 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1985 Cr and has been revised to ₹1798 Cr — a cost overrun of -9.4%. Expenditure to date: ₹1240 Cr (69.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Ratnagiri - Kolhapur section from km 67.140 to km 112. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618836. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Ratnagiri - Kolhapur section from km 67.140 to km 112. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.