Original Cost
₹1985 Cr
Baseline estimate
Revised Cost
₹1798 Cr
Latest approved cost
Expenditure
₹463 Cr
Spent to date
Utilization
25.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1335 Cr
Budget left
Spent
₹463 Cr
Remaining
₹1335 Cr
Total
₹1798 Cr
Project Approved
Construction / Implementation
Original End Date
24/05/2025
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1985 Cr — no cost escalation recorded.
Expenditure stands at ₹463 Cr, which is 25.8% of the revised project cost.
Remaining budget: ₹1335 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.