Original Cost
₹1939 Cr
Baseline estimate
Revised Cost
₹1910 Cr
Latest approved cost
Expenditure
₹483 Cr
Spent to date
Utilization
25.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1427 Cr
Budget left
Spent
₹483 Cr
Remaining
₹1427 Cr
Total
₹1910 Cr
Project Approved
Construction / Implementation
Original End Date
24/05/2025
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1939 Cr — no cost escalation recorded.
Expenditure stands at ₹483 Cr, which is 25.3% of the revised project cost.
Remaining budget: ₹1427 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.