Roads & HighwaysIPM · Central Project#618777

4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.717 of NH-71Package-II

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹593 CrUtilization: 45.0%

Original Cost

₹1877 Cr

Baseline estimate

On budget

Revised Cost

₹593 Cr

Latest approved cost

Expenditure

₹267 Cr

Spent to date

Utilization

45.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹326 Cr

Budget left

Budget Utilization

45.0%
0%25%50%75%100%

Spent

₹267 Cr

Remaining

₹326 Cr

Total

₹593 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

18/11/2025

Revised Completion

30/09/2026

Completed

Project Details

Project Code618777
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1877 Cr
Revised Cost₹593 Cr
Expenditure₹267 Cr
Original End Date18/11/2025
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹1877 Cr — no cost escalation recorded.

Expenditure stands at ₹267 Cr, which is 45.0% of the revised project cost.

Remaining budget: ₹326 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.717 of NH-71Package-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1877.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.7"?
4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.717 of NH-71Package-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹1877 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1877 Cr and has been revised to ₹593 Cr — a cost overrun of -68.4%. Expenditure to date: ₹267 Cr (45.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618777. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.