4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.717 of NH-71Package-II
Original Cost
₹1877 Cr
Baseline estimate
Revised Cost
₹593 Cr
Latest approved cost
Expenditure
₹267 Cr
Spent to date
Utilization
45.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹326 Cr
Budget left
Budget Utilization
45.0%Spent
₹267 Cr
Remaining
₹326 Cr
Total
₹593 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
18/11/2025
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1877 Cr — no cost escalation recorded.
Expenditure stands at ₹267 Cr, which is 45.0% of the revised project cost.
Remaining budget: ₹326 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.717 of NH-71Package-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1877.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.7"?
- 4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & Km 94.500 to Km 95.717 of NH-71Package-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹1877 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1877 Cr and has been revised to ₹593 Cr — a cost overrun of -68.4%. Expenditure to date: ₹267 Cr (45.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618777. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Pileru to Kalur Section from Km 55.900 to Km 92.800 & is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.