Roads & HighwaysIPM · Central Project#619113

4L of Padalur - Trichy section from km. 285.00 to km. 325.00 of NH - 45 Pkg VI-C

Ministry of Road Transport & HighwaysTamil Nadu
Revised Cost: ₹236 CrUtilization: 99.9%

Original Cost

₹556 Cr

Baseline estimate

On budget

Revised Cost

₹236 Cr

Latest approved cost

Expenditure

₹236 Cr

Spent to date

Utilization

99.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹0 Cr

Budget left

Budget Utilization

99.9%
0%25%50%75%100%

Spent

₹236 Cr

Remaining

₹0 Cr

Total

₹236 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/05/2009

Revised Completion

24/02/2026

Completed

Project Details

Project Code619113
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTamil Nadu
Data Month2026-06

Financial Summary

Original Cost₹556 Cr
Revised Cost₹236 Cr
Expenditure₹236 Cr
Original End Date24/05/2009
Revised Date24/02/2026

Project Intelligence

Project is within original budget of ₹556 Cr — no cost escalation recorded.

Expenditure stands at ₹236 Cr, which is 99.9% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Padalur - Trichy section from km. 285.00 to km. 325.00 of NH - 45 Pkg VI-C is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹556.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Padalur - Trichy section from km. 285.00 to km. 325.00 of NH - 45 Pkg VI-C"?
4L of Padalur - Trichy section from km. 285.00 to km. 325.00 of NH - 45 Pkg VI-C is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹556 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹556 Cr and has been revised to ₹236 Cr — a cost overrun of -57.6%. Expenditure to date: ₹236 Cr (99.9% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
4L of Padalur - Trichy section from km. 285.00 to km. 325.00 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619113. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Padalur - Trichy section from km. 285.00 to km. 325.00 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.