Original Cost
₹1770 Cr
Baseline estimate
Revised Cost
₹2025 Cr
Latest approved cost
Expenditure
₹574 Cr
Spent to date
Utilization
28.4%
Of revised budget
Cost Status
+14.4%
+₹255 Cr increase
Remaining
₹1450 Cr
Budget left
Spent
₹574 Cr
Remaining
₹1450 Cr
Total
₹2025 Cr
Original Cost
₹1770 Cr
Revised Cost
₹2025 Cr
Increase
+₹255 Cr
Escalation
+14.4%
Project Approved
Construction / Implementation
Original End Date
12/04/2024
Revised Completion
31/12/2026
Completed
Cost has increased by ₹255 Cr (14.4%) from the original estimate of ₹1770 Cr.
Expenditure stands at ₹574 Cr, which is 28.4% of the revised project cost.
Remaining budget: ₹1450 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.