Roads & HighwaysIPM · Central Project +21.0% overrun#619306

4L of Munger Mirzachauki section from Km 95580 to Km 125000 Pkg-2

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹1236 CrUtilization: 52.0%Overrun: +₹215 Cr

Original Cost

₹1021 Cr

Baseline estimate

+21% overrun

Revised Cost

₹1236 Cr

Latest approved cost

Expenditure

₹643 Cr

Spent to date

Utilization

52.0%

Of revised budget

Escalated

Cost Status

+21.0%

+₹215 Cr increase

Remaining

₹593 Cr

Budget left

Budget Utilization

52.0%
0%25%50%75%100%

Spent

₹643 Cr

Remaining

₹593 Cr

Total

₹1236 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1021 Cr

Revised Cost

₹1236 Cr

Increase

+₹215 Cr

Escalation

+21.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

10/03/2024

Revised Completion

30/09/2026

Completed

Project Details

Project Code619306
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹1021 Cr
Revised Cost₹1236 Cr
Expenditure₹643 Cr
Original End Date10/03/2024
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹215 Cr (21.0%) from the original estimate of ₹1021 Cr.

Expenditure stands at ₹643 Cr, which is 52.0% of the revised project cost.

Remaining budget: ₹593 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Munger Mirzachauki section from Km 95580 to Km 125000 Pkg-2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1021.00 Cr, later revised to ₹1235.65 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Munger Mirzachauki section from Km 95580 to Km 125000 Pkg-2"?
4L of Munger Mirzachauki section from Km 95580 to Km 125000 Pkg-2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹1021 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1021 Cr and has been revised to ₹1236 Cr — a cost overrun of +21%. Expenditure to date: ₹643 Cr (52.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Munger Mirzachauki section from Km 95580 to Km 125000 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619306. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Munger Mirzachauki section from Km 95580 to Km 125000 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.