Roads & HighwaysIPM · Central Project +7.6% overrun#619307

4L of Munger Mirzachauki section from Km 157350 to Km 193931 Pkg-4

Ministry of Road Transport & HighwaysJharkhand
Revised Cost: ₹1482 CrUtilization: 60.5%Overrun: +₹105 Cr

Original Cost

₹1377 Cr

Baseline estimate

+8% overrun

Revised Cost

₹1482 Cr

Latest approved cost

Expenditure

₹897 Cr

Spent to date

Utilization

60.5%

Of revised budget

Escalated

Cost Status

+7.6%

+₹105 Cr increase

Remaining

₹585 Cr

Budget left

Budget Utilization

60.5%
0%25%50%75%100%

Spent

₹897 Cr

Remaining

₹585 Cr

Total

₹1482 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1377 Cr

Revised Cost

₹1482 Cr

Increase

+₹105 Cr

Escalation

+7.6%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/08/2024

Revised Completion

31/10/2026

Completed

Project Details

Project Code619307
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹1377 Cr
Revised Cost₹1482 Cr
Expenditure₹897 Cr
Original End Date15/08/2024
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹105 Cr (7.6%) from the original estimate of ₹1377 Cr.

Expenditure stands at ₹897 Cr, which is 60.5% of the revised project cost.

Remaining budget: ₹585 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Munger Mirzachauki section from Km 157350 to Km 193931 Pkg-4 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1377.00 Cr, later revised to ₹1481.58 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Munger Mirzachauki section from Km 157350 to Km 193931 Pkg-4"?
4L of Munger Mirzachauki section from Km 157350 to Km 193931 Pkg-4 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹1377 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1377 Cr and has been revised to ₹1482 Cr — a cost overrun of +7.6%. Expenditure to date: ₹897 Cr (60.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Munger Mirzachauki section from Km 157350 to Km 19393 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619307. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Munger Mirzachauki section from Km 157350 to Km 19393 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.