Original Cost
₹1480 Cr
Baseline estimate
Revised Cost
₹1568 Cr
Latest approved cost
Expenditure
₹878 Cr
Spent to date
Utilization
56.0%
Of revised budget
Cost Status
+6.0%
+₹88 Cr increase
Remaining
₹690 Cr
Budget left
Spent
₹878 Cr
Remaining
₹690 Cr
Total
₹1568 Cr
Original Cost
₹1480 Cr
Revised Cost
₹1568 Cr
Increase
+₹88 Cr
Escalation
+6.0%
Project Approved
Construction / Implementation
Original End Date
07/05/2025
Revised Completion
30/06/2026
Completed
Cost has increased by ₹88 Cr (6.0%) from the original estimate of ₹1480 Cr.
Expenditure stands at ₹878 Cr, which is 56.0% of the revised project cost.
Remaining budget: ₹690 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.