Roads & HighwaysIPM · Central Project#618755

4L of left out existing road section from Lalgopalganj Km 161.450 to Nawabganj Km 180.200 in Prayagraj

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹101 CrUtilization: 71.9%

Original Cost

₹160 Cr

Baseline estimate

On budget

Revised Cost

₹101 Cr

Latest approved cost

Expenditure

₹72 Cr

Spent to date

Utilization

71.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹28 Cr

Budget left

Budget Utilization

71.9%
0%25%50%75%100%

Spent

₹72 Cr

Remaining

₹28 Cr

Total

₹101 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2026

Revised Completion

30/06/2026

Completed

Project Details

Project Code618755
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-05

Financial Summary

Original Cost₹160 Cr
Revised Cost₹101 Cr
Expenditure₹72 Cr
Original End Date31/03/2026
Revised Date30/06/2026

Project Intelligence

Project is within original budget of ₹160 Cr — no cost escalation recorded.

Expenditure stands at ₹72 Cr, which is 71.9% of the revised project cost.

Remaining budget: ₹28 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of left out existing road section from Lalgopalganj Km 161.450 to Nawabganj Km 180.200 in Prayagraj is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹160.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of left out existing road section from Lalgopalganj Km 161.450 to Nawabganj K"?
4L of left out existing road section from Lalgopalganj Km 161.450 to Nawabganj Km 180.200 in Prayagraj is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹160 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹160 Cr and has been revised to ₹101 Cr — a cost overrun of -37%. Expenditure to date: ₹72 Cr (71.9% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L of left out existing road section from Lalgopalganj Km 16 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618755. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of left out existing road section from Lalgopalganj Km 16 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.