Original Cost
₹614 Cr
Baseline estimate
Revised Cost
₹445 Cr
Latest approved cost
Expenditure
₹264 Cr
Spent to date
Utilization
59.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹181 Cr
Budget left
Spent
₹264 Cr
Remaining
₹181 Cr
Total
₹445 Cr
Project Approved
Construction / Implementation
Original End Date
03/08/2024
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹614 Cr — no cost escalation recorded.
Expenditure stands at ₹264 Cr, which is 59.3% of the revised project cost.
Remaining budget: ₹181 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.