Original Cost
₹2147 Cr
Baseline estimate
Revised Cost
₹2487 Cr
Latest approved cost
Expenditure
₹962 Cr
Spent to date
Utilization
38.7%
Of revised budget
Cost Status
+15.8%
+₹340 Cr increase
Remaining
₹1524 Cr
Budget left
Spent
₹962 Cr
Remaining
₹1524 Cr
Total
₹2487 Cr
Original Cost
₹2147 Cr
Revised Cost
₹2487 Cr
Increase
+₹340 Cr
Escalation
+15.8%
Project Approved
Construction / Implementation
Original End Date
16/07/2025
Revised Completion
31/07/2026
Completed
Cost has increased by ₹340 Cr (15.8%) from the original estimate of ₹2147 Cr.
Expenditure stands at ₹962 Cr, which is 38.7% of the revised project cost.
Remaining budget: ₹1524 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.