Roads & HighwaysIPM · Central Project#618875

4L of Haridwar Nagina section Design Ch. LME from km 13.829 to km 17.110 & km 26.077 to km 27.508 and Design Ch. RME from km 13.839 to km 17.120 & km 26.078 to km 27.509 of EUP mitigation measures on NH74

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹142 CrUtilization: 84.2%

Original Cost

₹184 Cr

Baseline estimate

On budget

Revised Cost

₹142 Cr

Latest approved cost

Expenditure

₹120 Cr

Spent to date

Utilization

84.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹22 Cr

Budget left

Budget Utilization

84.2%
0%25%50%75%100%

Spent

₹120 Cr

Remaining

₹22 Cr

Total

₹142 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/02/2024

Revised Completion

30/12/2026

Completed

Project Details

Project Code618875
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹184 Cr
Revised Cost₹142 Cr
Expenditure₹120 Cr
Original End Date27/02/2024
Revised Date30/12/2026

Project Intelligence

Project is within original budget of ₹184 Cr — no cost escalation recorded.

Expenditure stands at ₹120 Cr, which is 84.2% of the revised project cost.

Remaining budget: ₹22 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Haridwar Nagina section Design Ch. LME from km 13.829 to km 17.110 & km 26.077 to km 27.508 and Design Ch. RME from km 13.839 to km 17.120 & km 26.078 to km 27.509 of EUP mitigation measures on NH74 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹184.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Haridwar Nagina section Design Ch. LME from km 13.829 to km 17.110 & km 2"?
4L of Haridwar Nagina section Design Ch. LME from km 13.829 to km 17.110 & km 26.077 to km 27.508 and Design Ch. RME from km 13.839 to km 17.120 & km 26.078 to km 27.509 of EUP mitigation measures on NH74 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹184 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹184 Cr and has been revised to ₹142 Cr — a cost overrun of -22.8%. Expenditure to date: ₹120 Cr (84.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Haridwar Nagina section Design Ch. LME from km 13.829 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618875. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Haridwar Nagina section Design Ch. LME from km 13.829 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.