Original Cost
₹2186 Cr
Baseline estimate
Revised Cost
₹2118 Cr
Latest approved cost
Expenditure
₹765 Cr
Spent to date
Utilization
36.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1353 Cr
Budget left
Budget Utilization
36.1%Spent
₹765 Cr
Remaining
₹1353 Cr
Total
₹2118 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
10/03/2026
Revised Completion
30/03/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹2186 Cr — no cost escalation recorded.
Expenditure stands at ₹765 Cr, which is 36.1% of the revised project cost.
Remaining budget: ₹1353 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2186.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bel"?
- 4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹2186 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2186 Cr and has been revised to ₹2118 Cr — a cost overrun of -3.1%. Expenditure to date: ₹765 Cr (36.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619127. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.