Roads & HighwaysIPM · Central Project#619127

4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹2118 CrUtilization: 36.1%

Original Cost

₹2186 Cr

Baseline estimate

On budget

Revised Cost

₹2118 Cr

Latest approved cost

Expenditure

₹765 Cr

Spent to date

Utilization

36.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1353 Cr

Budget left

Budget Utilization

36.1%
0%25%50%75%100%

Spent

₹765 Cr

Remaining

₹1353 Cr

Total

₹2118 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

10/03/2026

Revised Completion

30/03/2028

Completed

Project Details

Project Code619127
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹2186 Cr
Revised Cost₹2118 Cr
Expenditure₹765 Cr
Original End Date10/03/2026
Revised Date30/03/2028

Project Intelligence

Project is within original budget of ₹2186 Cr — no cost escalation recorded.

Expenditure stands at ₹765 Cr, which is 36.1% of the revised project cost.

Remaining budget: ₹1353 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2186.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bel"?
4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹2186 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2186 Cr and has been revised to ₹2118 Cr — a cost overrun of -3.1%. Expenditure to date: ₹765 Cr (36.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619127. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.