Original Cost
₹2186 Cr
Baseline estimate
Revised Cost
₹2118 Cr
Latest approved cost
Expenditure
₹412 Cr
Spent to date
Utilization
19.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1707 Cr
Budget left
Spent
₹412 Cr
Remaining
₹1707 Cr
Total
₹2118 Cr
Project Approved
Construction / Implementation
Original End Date
10/03/2026
Revised Completion
30/03/2028
Completed
Project is within original budget of ₹2186 Cr — no cost escalation recorded.
Expenditure stands at ₹412 Cr, which is 19.4% of the revised project cost.
Remaining budget: ₹1707 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.