Original Cost
₹1008 Cr
Baseline estimate
Revised Cost
₹1031 Cr
Latest approved cost
Expenditure
₹439 Cr
Spent to date
Utilization
42.6%
Of revised budget
Cost Status
+2.2%
+₹23 Cr increase
Remaining
₹592 Cr
Budget left
Spent
₹439 Cr
Remaining
₹592 Cr
Total
₹1031 Cr
Original Cost
₹1008 Cr
Revised Cost
₹1031 Cr
Increase
+₹23 Cr
Escalation
+2.2%
Project Approved
Construction / Implementation
Original End Date
25/06/2025
Revised Completion
31/10/2026
Completed
Cost has increased by ₹23 Cr (2.2%) from the original estimate of ₹1008 Cr.
Expenditure stands at ₹439 Cr, which is 42.6% of the revised project cost.
Remaining budget: ₹592 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.