Original Cost
₹828 Cr
Baseline estimate
Revised Cost
₹828 Cr
Latest approved cost
Expenditure
₹25 Cr
Spent to date
Utilization
3.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹803 Cr
Budget left
Spent
₹25 Cr
Remaining
₹803 Cr
Total
₹828 Cr
Project Approved
Construction / Implementation
Original End Date
18/05/2028
Revised Completion
18/05/2028
Completed
Project is within original budget of ₹828 Cr — no cost escalation recorded.
Expenditure stands at ₹25 Cr, which is 3.0% of the revised project cost.
Remaining budget: ₹803 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.