4L of existing 2/4L stretch from Lonand to Dive Ghat Km 166.400 to Km 220.900 of Mohol Alandi section of NH-965 Pkg - V

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹2050 CrUtilization: 54.9%Overrun: +₹340 Cr

Original Cost

₹1710 Cr

Baseline estimate

+20% overrun

Revised Cost

₹2050 Cr

Latest approved cost

Expenditure

₹1126 Cr

Spent to date

Utilization

54.9%

Of revised budget

Escalated

Cost Status

+19.9%

+₹340 Cr increase

Remaining

₹924 Cr

Budget left

Budget Utilization

54.9%
0%25%50%75%100%

Spent

₹1126 Cr

Remaining

₹924 Cr

Total

₹2050 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1710 Cr

Revised Cost

₹2050 Cr

Increase

+₹340 Cr

Escalation

+19.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/05/2024

Revised Completion

30/04/2026

Completed

Project Details

Project Code619209
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-05

Financial Summary

Original Cost₹1710 Cr
Revised Cost₹2050 Cr
Expenditure₹1126 Cr
Original End Date02/05/2024
Revised Date30/04/2026

Project Intelligence

Cost has increased by ₹340 Cr (19.9%) from the original estimate of ₹1710 Cr.

Expenditure stands at ₹1126 Cr, which is 54.9% of the revised project cost.

Remaining budget: ₹924 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of existing 2/4L stretch from Lonand to Dive Ghat Km 166.400 to Km 220.900 of Mohol Alandi section of NH-965 Pkg - V is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1710.00 Cr, later revised to ₹2049.51 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of existing 2/4L stretch from Lonand to Dive Ghat Km 166.400 to Km 220.900 "?
4L of existing 2/4L stretch from Lonand to Dive Ghat Km 166.400 to Km 220.900 of Mohol Alandi section of NH-965 Pkg - V is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹1710 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1710 Cr and has been revised to ₹2050 Cr — a cost overrun of +19.9%. Expenditure to date: ₹1126 Cr (54.9% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L of existing 2/4L stretch from Lonand to Dive Ghat Km 166 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619209. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of existing 2/4L stretch from Lonand to Dive Ghat Km 166 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.