Roads & HighwaysIPM · Central Project +71.1% overrun#619137

4L of Dwarka-Khambaliya-Devariya section from km 203.500 to km 176.500 and from km 171.800 to km 125.000 of NH-151A

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹1754 CrUtilization: 50.3%Overrun: +₹729 Cr

Original Cost

₹1025 Cr

Baseline estimate

+71% overrun

Revised Cost

₹1754 Cr

Latest approved cost

Expenditure

₹882 Cr

Spent to date

Utilization

50.3%

Of revised budget

Escalated

Cost Status

+71.1%

+₹729 Cr increase

Remaining

₹872 Cr

Budget left

Budget Utilization

50.3%
0%25%50%75%100%

Spent

₹882 Cr

Remaining

₹872 Cr

Total

₹1754 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1025 Cr

Revised Cost

₹1754 Cr

Increase

+₹729 Cr

Escalation

+71.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/08/2022

Revised Completion

31/05/2026

Completed

Project Details

Project Code619137
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-04

Financial Summary

Original Cost₹1025 Cr
Revised Cost₹1754 Cr
Expenditure₹882 Cr
Original End Date07/08/2022
Revised Date31/05/2026

Project Intelligence

Cost has increased by ₹729 Cr (71.1%) from the original estimate of ₹1025 Cr.

Expenditure stands at ₹882 Cr, which is 50.3% of the revised project cost.

Remaining budget: ₹872 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Dwarka-Khambaliya-Devariya section from km 203.500 to km 176.500 and from km 171.800 to km 125.000 of NH-151A is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1025.00 Cr, later revised to ₹1753.95 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Dwarka-Khambaliya-Devariya section from km 203.500 to km 176.500 and from "?
4L of Dwarka-Khambaliya-Devariya section from km 203.500 to km 176.500 and from km 171.800 to km 125.000 of NH-151A is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1025 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1025 Cr and has been revised to ₹1754 Cr — a cost overrun of +71.1%. Expenditure to date: ₹882 Cr (50.3% of revised cost). Data as of 2026-04.
QWhich ministry is responsible for this project?
4L of Dwarka-Khambaliya-Devariya section from km 203.500 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619137. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Dwarka-Khambaliya-Devariya section from km 203.500 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.