Original Cost
₹996 Cr
Baseline estimate
Revised Cost
₹847 Cr
Latest approved cost
Expenditure
₹137 Cr
Spent to date
Utilization
16.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹709 Cr
Budget left
Spent
₹137 Cr
Remaining
₹709 Cr
Total
₹847 Cr
Project Approved
Construction / Implementation
Original End Date
21/09/2027
Revised Completion
21/09/2027
Completed
Project is within original budget of ₹996 Cr — no cost escalation recorded.
Expenditure stands at ₹137 Cr, which is 16.2% of the revised project cost.
Remaining budget: ₹709 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.