Original Cost
₹910 Cr
Baseline estimate
Revised Cost
₹977 Cr
Latest approved cost
Expenditure
₹436 Cr
Spent to date
Utilization
44.7%
Of revised budget
Cost Status
+7.3%
+₹67 Cr increase
Remaining
₹540 Cr
Budget left
Spent
₹436 Cr
Remaining
₹540 Cr
Total
₹977 Cr
Original Cost
₹910 Cr
Revised Cost
₹977 Cr
Increase
+₹67 Cr
Escalation
+7.3%
Project Approved
Construction / Implementation
Original End Date
31/05/2024
Revised Completion
30/09/2026
Completed
Cost has increased by ₹67 Cr (7.3%) from the original estimate of ₹910 Cr.
Expenditure stands at ₹436 Cr, which is 44.7% of the revised project cost.
Remaining budget: ₹540 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.