Original Cost
₹1856 Cr
Baseline estimate
Revised Cost
₹2524 Cr
Latest approved cost
Expenditure
₹1295 Cr
Spent to date
Utilization
51.3%
Of revised budget
Cost Status
+36.0%
+₹668 Cr increase
Remaining
₹1229 Cr
Budget left
Spent
₹1295 Cr
Remaining
₹1229 Cr
Total
₹2524 Cr
Original Cost
₹1856 Cr
Revised Cost
₹2524 Cr
Increase
+₹668 Cr
Escalation
+36.0%
Project Approved
Construction / Implementation
Original End Date
24/03/2024
Revised Completion
31/07/2026
Completed
Cost has increased by ₹668 Cr (36.0%) from the original estimate of ₹1856 Cr.
Expenditure stands at ₹1295 Cr, which is 51.3% of the revised project cost.
Remaining budget: ₹1229 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.