Roads & HighwaysIPM · Central Project +13.3% overrun#619148

4L of Bhavnagar - Talaja Package-I from Km. 6.945 to Km. 54.990 of Old NH-8E

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹1343 CrUtilization: 4.0%Overrun: +₹157 Cr

Original Cost

₹1186 Cr

Baseline estimate

+13% overrun

Revised Cost

₹1343 Cr

Latest approved cost

Expenditure

₹53 Cr

Spent to date

Utilization

4.0%

Of revised budget

Escalated

Cost Status

+13.3%

+₹157 Cr increase

Remaining

₹1290 Cr

Budget left

Budget Utilization

4.0%
0%25%50%75%100%

Spent

₹53 Cr

Remaining

₹1290 Cr

Total

₹1343 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1186 Cr

Revised Cost

₹1343 Cr

Increase

+₹157 Cr

Escalation

+13.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/08/2019

Revised Completion

Completed

Project Details

Project Code619148
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-05

Financial Summary

Original Cost₹1186 Cr
Revised Cost₹1343 Cr
Expenditure₹53 Cr
Original End Date06/08/2019
Revised DateN/A

Project Intelligence

Cost has increased by ₹157 Cr (13.3%) from the original estimate of ₹1186 Cr.

Expenditure stands at ₹53 Cr, which is 4.0% of the revised project cost.

Remaining budget: ₹1290 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Bhavnagar - Talaja Package-I from Km. 6.945 to Km. 54.990 of Old NH-8E is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1186.00 Cr, later revised to ₹1343.16 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Bhavnagar - Talaja Package-I from Km. 6.945 to Km. 54.990 of Old NH-8E"?
4L of Bhavnagar - Talaja Package-I from Km. 6.945 to Km. 54.990 of Old NH-8E is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹1186 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1186 Cr and has been revised to ₹1343 Cr — a cost overrun of +13.3%. Expenditure to date: ₹53 Cr (4.0% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L of Bhavnagar - Talaja Package-I from Km. 6.945 to Km. 54. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619148. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Bhavnagar - Talaja Package-I from Km. 6.945 to Km. 54. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.