Roads & HighwaysIPM · Central Project +19.4% overrun#618809

4L of Beas-Mehta-Batala-Dera Baba Nanak from intersection with Jalandhar-Amritsar Highway NH-3 near Beas till start of Batala Bypass near Village Acchhal from Km. 0.000 to Km. 31.300 Pkg-1

Ministry of Road Transport & HighwaysPunjab
Revised Cost: ₹967 CrUtilization: 72.5%Overrun: +₹157 Cr

Original Cost

₹810 Cr

Baseline estimate

+19% overrun

Revised Cost

₹967 Cr

Latest approved cost

Expenditure

₹701 Cr

Spent to date

Utilization

72.5%

Of revised budget

Escalated

Cost Status

+19.4%

+₹157 Cr increase

Remaining

₹266 Cr

Budget left

Budget Utilization

72.5%
0%25%50%75%100%

Spent

₹701 Cr

Remaining

₹266 Cr

Total

₹967 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹810 Cr

Revised Cost

₹967 Cr

Increase

+₹157 Cr

Escalation

+19.4%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

21/06/2025

Revised Completion

31/05/2027

Completed

Project Details

Project Code618809
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹810 Cr
Revised Cost₹967 Cr
Expenditure₹701 Cr
Original End Date21/06/2025
Revised Date31/05/2027

Project Intelligence

Cost has increased by ₹157 Cr (19.4%) from the original estimate of ₹810 Cr.

Expenditure stands at ₹701 Cr, which is 72.5% of the revised project cost.

Remaining budget: ₹266 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Beas-Mehta-Batala-Dera Baba Nanak from intersection with Jalandhar-Amritsar Highway NH-3 near Beas till start of Batala Bypass near Village Acchhal from Km. 0.000 to Km. 31.300 Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹810.00 Cr, later revised to ₹966.99 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Beas-Mehta-Batala-Dera Baba Nanak from intersection with Jalandhar-Amritsa"?
4L of Beas-Mehta-Batala-Dera Baba Nanak from intersection with Jalandhar-Amritsar Highway NH-3 near Beas till start of Batala Bypass near Village Acchhal from Km. 0.000 to Km. 31.300 Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹810 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹810 Cr and has been revised to ₹967 Cr — a cost overrun of +19.4%. Expenditure to date: ₹701 Cr (72.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Beas-Mehta-Batala-Dera Baba Nanak from intersection wi is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618809. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Beas-Mehta-Batala-Dera Baba Nanak from intersection wi is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.