Roads & HighwaysIPM · Central Project +68.2% overrun#618906

4L of Amritsar-Ghoman - Tanda - Una Section from Km 8.270 to Km 54.000 of NH-503A Package-I

Ministry of Road Transport & HighwaysPunjab
Revised Cost: ₹1443 CrUtilization: 53.6%Overrun: +₹585 Cr

Original Cost

₹858 Cr

Baseline estimate

+68% overrun

Revised Cost

₹1443 Cr

Latest approved cost

Expenditure

₹773 Cr

Spent to date

Utilization

53.6%

Of revised budget

Escalated

Cost Status

+68.2%

+₹585 Cr increase

Remaining

₹670 Cr

Budget left

Budget Utilization

53.6%
0%25%50%75%100%

Spent

₹773 Cr

Remaining

₹670 Cr

Total

₹1443 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹858 Cr

Revised Cost

₹1443 Cr

Increase

+₹585 Cr

Escalation

+68.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

19/06/2024

Revised Completion

31/03/2027

Completed

Project Details

Project Code618906
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹858 Cr
Revised Cost₹1443 Cr
Expenditure₹773 Cr
Original End Date19/06/2024
Revised Date31/03/2027

Project Intelligence

Cost has increased by ₹585 Cr (68.2%) from the original estimate of ₹858 Cr.

Expenditure stands at ₹773 Cr, which is 53.6% of the revised project cost.

Remaining budget: ₹670 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Amritsar-Ghoman - Tanda - Una Section from Km 8.270 to Km 54.000 of NH-503A Package-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹858.00 Cr, later revised to ₹1443.47 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Amritsar-Ghoman - Tanda - Una Section from Km 8.270 to Km 54.000 of NH-503"?
4L of Amritsar-Ghoman - Tanda - Una Section from Km 8.270 to Km 54.000 of NH-503A Package-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹858 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹858 Cr and has been revised to ₹1443 Cr — a cost overrun of +68.2%. Expenditure to date: ₹773 Cr (53.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Amritsar-Ghoman - Tanda - Una Section from Km 8.270 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618906. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Amritsar-Ghoman - Tanda - Una Section from Km 8.270 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.