Roads & HighwaysIPM · Central Project#618702

4L of Addahole Near Gundya to Bantwal Cross section Pkg-02 from Design Km 270.270 to Design km 318.55 including flyover at Kalladka Town including approaches from Km. 311.57 to Km. 313.67 of NH-75 Old NH-48

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹1318 CrUtilization: 110.2%

Original Cost

₹1660 Cr

Baseline estimate

On budget

Revised Cost

₹1318 Cr

Latest approved cost

Expenditure

₹1452 Cr

Spent to date

Utilization

110.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹0 Cr

Budget left

Budget Utilization

110.2%
0%25%50%75%100%

Spent

₹1452 Cr

Remaining

₹0 Cr

Total

₹1318 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/11/2023

Revised Completion

30/04/2027

Completed

Project Details

Project Code618702
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹1660 Cr
Revised Cost₹1318 Cr
Expenditure₹1452 Cr
Original End Date22/11/2023
Revised Date30/04/2027

Project Intelligence

Project is within original budget of ₹1660 Cr — no cost escalation recorded.

Expenditure stands at ₹1452 Cr, which is 110.2% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Addahole Near Gundya to Bantwal Cross section Pkg-02 from Design Km 270.270 to Design km 318.55 including flyover at Kalladka Town including approaches from Km. 311.57 to Km. 313.67 of NH-75 Old NH-48 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1660.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Addahole Near Gundya to Bantwal Cross section Pkg-02 from Design Km 270.27"?
4L of Addahole Near Gundya to Bantwal Cross section Pkg-02 from Design Km 270.270 to Design km 318.55 including flyover at Kalladka Town including approaches from Km. 311.57 to Km. 313.67 of NH-75 Old NH-48 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1660 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1660 Cr and has been revised to ₹1318 Cr — a cost overrun of -20.6%. Expenditure to date: ₹1452 Cr (110.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Addahole Near Gundya to Bantwal Cross section Pkg-02 f is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618702. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Addahole Near Gundya to Bantwal Cross section Pkg-02 f is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.