4L Medinipur to Ballupur from Km. 458.65 to Km. 487.65 of NH-07Pkg-2
Original Cost
₹1093 Cr
Baseline estimate
Revised Cost
₹1073 Cr
Latest approved cost
Expenditure
₹745 Cr
Spent to date
Utilization
69.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹327 Cr
Budget left
Budget Utilization
69.5%Spent
₹745 Cr
Remaining
₹327 Cr
Total
₹1073 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/02/2025
Revised Completion
15/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1093 Cr — no cost escalation recorded.
Expenditure stands at ₹745 Cr, which is 69.5% of the revised project cost.
Remaining budget: ₹327 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Medinipur to Ballupur from Km. 458.65 to Km. 487.65 of NH-07Pkg-2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1093.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Medinipur to Ballupur from Km. 458.65 to Km. 487.65 of NH-07Pkg-2"?
- 4L Medinipur to Ballupur from Km. 458.65 to Km. 487.65 of NH-07Pkg-2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹1093 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1093 Cr and has been revised to ₹1073 Cr — a cost overrun of -1.9%. Expenditure to date: ₹745 Cr (69.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Medinipur to Ballupur from Km. 458.65 to Km. 487.65 of NH is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619292. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Medinipur to Ballupur from Km. 458.65 to Km. 487.65 of NH is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.