Original Cost
₹1093 Cr
Baseline estimate
Revised Cost
₹1073 Cr
Latest approved cost
Expenditure
₹736 Cr
Spent to date
Utilization
68.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹336 Cr
Budget left
Spent
₹736 Cr
Remaining
₹336 Cr
Total
₹1073 Cr
Project Approved
Construction / Implementation
Original End Date
17/02/2025
Revised Completion
15/07/2026
Completed
Project is within original budget of ₹1093 Cr — no cost escalation recorded.
Expenditure stands at ₹736 Cr, which is 68.6% of the revised project cost.
Remaining budget: ₹336 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.