4L Kasganj-Badaun Section from Km. 123.100 to Km. 179.500 Pkg-III of NH530B
Original Cost
₹2009 Cr
Baseline estimate
Revised Cost
₹1937 Cr
Latest approved cost
Expenditure
₹593 Cr
Spent to date
Utilization
30.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1343 Cr
Budget left
Budget Utilization
30.6%Spent
₹593 Cr
Remaining
₹1343 Cr
Total
₹1937 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
29/05/2027
Revised Completion
31/12/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹2009 Cr — no cost escalation recorded.
Expenditure stands at ₹593 Cr, which is 30.6% of the revised project cost.
Remaining budget: ₹1343 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Kasganj-Badaun Section from Km. 123.100 to Km. 179.500 Pkg-III of NH530B is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2009.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Kasganj-Badaun Section from Km. 123.100 to Km. 179.500 Pkg-III of NH530B"?
- 4L Kasganj-Badaun Section from Km. 123.100 to Km. 179.500 Pkg-III of NH530B is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹2009 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2009 Cr and has been revised to ₹1937 Cr — a cost overrun of -3.6%. Expenditure to date: ₹593 Cr (30.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Kasganj-Badaun Section from Km. 123.100 to Km. 179.500 Pk is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618867. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Kasganj-Badaun Section from Km. 123.100 to Km. 179.500 Pk is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.