4L Ismailabad to Ambala Section of NH-152 Lot-4/Package-1
Original Cost
₹609 Cr
Baseline estimate
Revised Cost
₹454 Cr
Latest approved cost
Expenditure
₹311 Cr
Spent to date
Utilization
68.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹143 Cr
Budget left
Budget Utilization
68.5%Spent
₹311 Cr
Remaining
₹143 Cr
Total
₹454 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/12/2025
Revised Completion
28/02/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹609 Cr — no cost escalation recorded.
Expenditure stands at ₹311 Cr, which is 68.5% of the revised project cost.
Remaining budget: ₹143 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Ismailabad to Ambala Section of NH-152 Lot-4/Package-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹609.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Ismailabad to Ambala Section of NH-152 Lot-4/Package-1"?
- 4L Ismailabad to Ambala Section of NH-152 Lot-4/Package-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹609 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹609 Cr and has been revised to ₹454 Cr — a cost overrun of -25.4%. Expenditure to date: ₹311 Cr (68.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Ismailabad to Ambala Section of NH-152 Lot-4/Package-1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619093. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Ismailabad to Ambala Section of NH-152 Lot-4/Package-1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.