Original Cost
₹1636 Cr
Baseline estimate
Revised Cost
₹2170 Cr
Latest approved cost
Expenditure
₹1278 Cr
Spent to date
Utilization
58.9%
Of revised budget
Cost Status
+32.7%
+₹534 Cr increase
Remaining
₹892 Cr
Budget left
Spent
₹1278 Cr
Remaining
₹892 Cr
Total
₹2170 Cr
Original Cost
₹1636 Cr
Revised Cost
₹2170 Cr
Increase
+₹534 Cr
Escalation
+32.7%
Project Approved
Construction / Implementation
Original End Date
10/11/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹534 Cr (32.7%) from the original estimate of ₹1636 Cr.
Expenditure stands at ₹1278 Cr, which is 58.9% of the revised project cost.
Remaining budget: ₹892 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.