Original Cost
₹609 Cr
Baseline estimate
Revised Cost
₹560 Cr
Latest approved cost
Expenditure
₹535 Cr
Spent to date
Utilization
95.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹25 Cr
Budget left
Spent
₹535 Cr
Remaining
₹25 Cr
Total
₹560 Cr
Project Approved
Construction / Implementation
Original End Date
24/09/2025
Revised Completion
31/01/2027
Completed
Project is within original budget of ₹609 Cr — no cost escalation recorded.
Expenditure stands at ₹535 Cr, which is 95.6% of the revised project cost.
Remaining budget: ₹25 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.