4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D Pkg-II
Original Cost
₹1494 Cr
Baseline estimate
Revised Cost
₹1546 Cr
Latest approved cost
Expenditure
₹706 Cr
Spent to date
Utilization
45.7%
Of revised budget
Cost Status
+3.5%
+₹52 Cr increase
Remaining
₹840 Cr
Budget left
Budget Utilization
45.7%Spent
₹706 Cr
Remaining
₹840 Cr
Total
₹1546 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1494 Cr
Revised Cost
₹1546 Cr
Increase
+₹52 Cr
Escalation
+3.5%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
03/07/2025
Revised Completion
30/11/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹52 Cr (3.5%) from the original estimate of ₹1494 Cr.
Expenditure stands at ₹706 Cr, which is 45.7% of the revised project cost.
Remaining budget: ₹840 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D Pkg-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1494.00 Cr, later revised to ₹1546.07 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.30"?
- 4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D Pkg-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹1494 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1494 Cr and has been revised to ₹1546 Cr — a cost overrun of +3.5%. Expenditure to date: ₹706 Cr (45.7% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Greenfield Alignment of Shivrampur to Ramnagar from Km. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618740. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Greenfield Alignment of Shivrampur to Ramnagar from Km. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.