Original Cost
₹1494 Cr
Baseline estimate
Revised Cost
₹1546 Cr
Latest approved cost
Expenditure
₹282 Cr
Spent to date
Utilization
18.3%
Of revised budget
Cost Status
+3.5%
+₹52 Cr increase
Remaining
₹1264 Cr
Budget left
Spent
₹282 Cr
Remaining
₹1264 Cr
Total
₹1546 Cr
Original Cost
₹1494 Cr
Revised Cost
₹1546 Cr
Increase
+₹52 Cr
Escalation
+3.5%
Project Approved
Construction / Implementation
Original End Date
03/07/2025
Revised Completion
30/11/2027
Completed
Cost has increased by ₹52 Cr (3.5%) from the original estimate of ₹1494 Cr.
Expenditure stands at ₹282 Cr, which is 18.3% of the revised project cost.
Remaining budget: ₹1264 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.