Roads & HighwaysIPM · Central Project#618760

4L Greenfield a Malout bypass from ch. Km 44.500 to ch. Km 35.500 on NH-07 and Ch. Km 0.000 to Km 6.984 on NH-09 bMandi Dabwali Bypass from Ch. 38.450 Km to Km 27.910 Pkg-02

Ministry of Road Transport & HighwaysHaryana
Revised Cost: ₹556 CrUtilization: 98.8%

Original Cost

₹646 Cr

Baseline estimate

On budget

Revised Cost

₹556 Cr

Latest approved cost

Expenditure

₹549 Cr

Spent to date

Utilization

98.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹7 Cr

Budget left

Budget Utilization

98.8%
0%25%50%75%100%

Spent

₹549 Cr

Remaining

₹7 Cr

Total

₹556 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

01/07/2024

Revised Completion

30/04/2026

Completed

Project Details

Project Code618760
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHaryana
Data Month2026-05

Financial Summary

Original Cost₹646 Cr
Revised Cost₹556 Cr
Expenditure₹549 Cr
Original End Date01/07/2024
Revised Date30/04/2026

Project Intelligence

Project is within original budget of ₹646 Cr — no cost escalation recorded.

Expenditure stands at ₹549 Cr, which is 98.8% of the revised project cost.

Remaining budget: ₹7 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Greenfield a Malout bypass from ch. Km 44.500 to ch. Km 35.500 on NH-07 and Ch. Km 0.000 to Km 6.984 on NH-09 bMandi Dabwali Bypass from Ch. 38.450 Km to Km 27.910 Pkg-02 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹646.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Greenfield a Malout bypass from ch. Km 44.500 to ch. Km 35.500 on NH-07 and C"?
4L Greenfield a Malout bypass from ch. Km 44.500 to ch. Km 35.500 on NH-07 and Ch. Km 0.000 to Km 6.984 on NH-09 bMandi Dabwali Bypass from Ch. 38.450 Km to Km 27.910 Pkg-02 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Haryana. Original cost: ₹646 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹646 Cr and has been revised to ₹556 Cr — a cost overrun of -13.9%. Expenditure to date: ₹549 Cr (98.8% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L Greenfield a Malout bypass from ch. Km 44.500 to ch. Km 3 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618760. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Greenfield a Malout bypass from ch. Km 44.500 to ch. Km 3 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.