4L from km 196.87 Sankha to km 219.6 Khajuri on NH-75 [Rehla / Garhwa Bypass]

Ministry of Road Transport & HighwaysJharkhand
Revised Cost: ₹1129 CrUtilization: 46.7%

Original Cost

₹1129 Cr

Baseline estimate

On budget

Revised Cost

₹1129 Cr

Latest approved cost

Expenditure

₹527 Cr

Spent to date

Utilization

46.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹602 Cr

Budget left

Budget Utilization

46.7%
0%25%50%75%100%

Spent

₹527 Cr

Remaining

₹602 Cr

Total

₹1129 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/10/2023

Revised Completion

Completed

Project Details

Project Code618829
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJharkhand
Data Month2026-05

Financial Summary

Original Cost₹1129 Cr
Revised Cost₹1129 Cr
Expenditure₹527 Cr
Original End Date06/10/2023
Revised DateN/A

Project Intelligence

Project is within original budget of ₹1129 Cr — no cost escalation recorded.

Expenditure stands at ₹527 Cr, which is 46.7% of the revised project cost.

Remaining budget: ₹602 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L from km 196.87 Sankha to km 219.6 Khajuri on NH-75 [Rehla / Garhwa Bypass] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1129.00 Cr, later revised to ₹1129.48 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L from km 196.87 Sankha to km 219.6 Khajuri on NH-75 [Rehla / Garhwa Bypass]"?
4L from km 196.87 Sankha to km 219.6 Khajuri on NH-75 [Rehla / Garhwa Bypass] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹1129 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1129 Cr has not been significantly revised. Expenditure: ₹527 Cr (46.7% of cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L from km 196.87 Sankha to km 219.6 Khajuri on NH-75 [Rehla is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618829. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L from km 196.87 Sankha to km 219.6 Khajuri on NH-75 [Rehla is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.