Original Cost
₹1518 Cr
Baseline estimate
Revised Cost
₹1652 Cr
Latest approved cost
Expenditure
₹992 Cr
Spent to date
Utilization
60.1%
Of revised budget
Cost Status
+8.8%
+₹134 Cr increase
Remaining
₹660 Cr
Budget left
Spent
₹992 Cr
Remaining
₹660 Cr
Total
₹1652 Cr
Original Cost
₹1518 Cr
Revised Cost
₹1652 Cr
Increase
+₹134 Cr
Escalation
+8.8%
Project Approved
Construction / Implementation
Original End Date
08/11/2025
Revised Completion
31/03/2027
Completed
Cost has increased by ₹134 Cr (8.8%) from the original estimate of ₹1518 Cr.
Expenditure stands at ₹992 Cr, which is 60.1% of the revised project cost.
Remaining budget: ₹660 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.