Original Cost
₹936 Cr
Baseline estimate
Revised Cost
₹832 Cr
Latest approved cost
Expenditure
₹294 Cr
Spent to date
Utilization
35.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹538 Cr
Budget left
Spent
₹294 Cr
Remaining
₹538 Cr
Total
₹832 Cr
Project Approved
Construction / Implementation
Original End Date
15/03/2027
Revised Completion
15/03/2027
Completed
Project is within original budget of ₹936 Cr — no cost escalation recorded.
Expenditure stands at ₹294 Cr, which is 35.4% of the revised project cost.
Remaining budget: ₹538 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.