Roads & HighwaysIPM · Central Project#618736

4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH-33 New NH-18 from km 241940 to km 251961 Length 10.021 km

Ministry of Road Transport & HighwaysJharkhand
Revised Cost: ₹832 CrUtilization: 41.6%

Original Cost

₹936 Cr

Baseline estimate

On budget

Revised Cost

₹832 Cr

Latest approved cost

Expenditure

₹347 Cr

Spent to date

Utilization

41.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹486 Cr

Budget left

Budget Utilization

41.6%
0%25%50%75%100%

Spent

₹347 Cr

Remaining

₹486 Cr

Total

₹832 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

15/03/2027

Revised Completion

15/03/2027

Completed

Project Details

Project Code618736
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJharkhand
Data Month2026-08

Financial Summary

Original Cost₹936 Cr
Revised Cost₹832 Cr
Expenditure₹347 Cr
Original End Date15/03/2027
Revised Date15/03/2027

Project Intelligence

Project is within original budget of ₹936 Cr — no cost escalation recorded.

Expenditure stands at ₹347 Cr, which is 41.6% of the revised project cost.

Remaining budget: ₹486 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH-33 New NH-18 from km 241940 to km 251961 Length 10.021 km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹936.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH"?
4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH-33 New NH-18 from km 241940 to km 251961 Length 10.021 km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹936 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹936 Cr and has been revised to ₹832 Cr — a cost overrun of -11.1%. Expenditure to date: ₹347 Cr (41.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jams is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618736. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jams is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.