4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH-33 New NH-18 from km 241940 to km 251961 Length 10.021 km
Original Cost
₹936 Cr
Baseline estimate
Revised Cost
₹832 Cr
Latest approved cost
Expenditure
₹347 Cr
Spent to date
Utilization
41.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹486 Cr
Budget left
Budget Utilization
41.6%Spent
₹347 Cr
Remaining
₹486 Cr
Total
₹832 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
15/03/2027
Revised Completion
15/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹936 Cr — no cost escalation recorded.
Expenditure stands at ₹347 Cr, which is 41.6% of the revised project cost.
Remaining budget: ₹486 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH-33 New NH-18 from km 241940 to km 251961 Length 10.021 km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹936.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH"?
- 4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jamshedpur Section of NH-33 New NH-18 from km 241940 to km 251961 Length 10.021 km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jharkhand. Original cost: ₹936 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹936 Cr and has been revised to ₹832 Cr — a cost overrun of -11.1%. Expenditure to date: ₹347 Cr (41.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jams is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618736. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Elevated corridor of Kalimandir-Dimna Chowk-Baliguma Jams is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.