Original Cost
₹1128 Cr
Baseline estimate
Revised Cost
₹1104 Cr
Latest approved cost
Expenditure
₹111 Cr
Spent to date
Utilization
10.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹993 Cr
Budget left
Spent
₹111 Cr
Remaining
₹993 Cr
Total
₹1104 Cr
Project Approved
Construction / Implementation
Original End Date
22/12/2026
Revised Completion
31/10/2027
Completed
Project is within original budget of ₹1128 Cr — no cost escalation recorded.
Expenditure stands at ₹111 Cr, which is 10.1% of the revised project cost.
Remaining budget: ₹993 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.