Roads & HighwaysIPM · Central Project#618813

4L Access Controlled Greenfield Section Mancherial Warangal from Narva village at Design Ch. 3.834 Km to Puttapaka village at Design Ch. 35.300 Km Package-I

Ministry of Road Transport & HighwaysTelangana
Revised Cost: ₹1104 CrUtilization: 14.7%

Original Cost

₹1128 Cr

Baseline estimate

On budget

Revised Cost

₹1104 Cr

Latest approved cost

Expenditure

₹162 Cr

Spent to date

Utilization

14.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹942 Cr

Budget left

Budget Utilization

14.7%
0%25%50%75%100%

Spent

₹162 Cr

Remaining

₹942 Cr

Total

₹1104 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/12/2026

Revised Completion

31/10/2027

Completed

Project Details

Project Code618813
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹1128 Cr
Revised Cost₹1104 Cr
Expenditure₹162 Cr
Original End Date22/12/2026
Revised Date31/10/2027

Project Intelligence

Project is within original budget of ₹1128 Cr — no cost escalation recorded.

Expenditure stands at ₹162 Cr, which is 14.7% of the revised project cost.

Remaining budget: ₹942 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Access Controlled Greenfield Section Mancherial Warangal from Narva village at Design Ch. 3.834 Km to Puttapaka village at Design Ch. 35.300 Km Package-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1128.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Access Controlled Greenfield Section Mancherial Warangal from Narva village "?
4L Access Controlled Greenfield Section Mancherial Warangal from Narva village at Design Ch. 3.834 Km to Puttapaka village at Design Ch. 35.300 Km Package-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹1128 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1128 Cr and has been revised to ₹1104 Cr — a cost overrun of -2.1%. Expenditure to date: ₹162 Cr (14.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L Access Controlled Greenfield Section Mancherial Warangal is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618813. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Access Controlled Greenfield Section Mancherial Warangal is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.