4L Access Controlled Greenfield Highway section on NH-163G Khammam Vijayawada from V. Venkatayapalem village at Design Ch. 220.480 Km to BrahmanapalliK village at Design Ch. 250.400 Km Package-I.
Original Cost
₹973 Cr
Baseline estimate
Revised Cost
₹1022 Cr
Latest approved cost
Expenditure
₹272 Cr
Spent to date
Utilization
26.6%
Of revised budget
Cost Status
+5.0%
+₹49 Cr increase
Remaining
₹750 Cr
Budget left
Budget Utilization
26.6%Spent
₹272 Cr
Remaining
₹750 Cr
Total
₹1022 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹973 Cr
Revised Cost
₹1022 Cr
Increase
+₹49 Cr
Escalation
+5.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
18/03/2027
Revised Completion
30/06/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹49 Cr (5.0%) from the original estimate of ₹973 Cr.
Expenditure stands at ₹272 Cr, which is 26.6% of the revised project cost.
Remaining budget: ₹750 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Access Controlled Greenfield Highway section on NH-163G Khammam Vijayawada from V. Venkatayapalem village at Design Ch. 220.480 Km to BrahmanapalliK village at Design Ch. 250.400 Km Package-I. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹973.00 Cr, later revised to ₹1021.96 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Access Controlled Greenfield Highway section on NH-163G Khammam Vijayawada fr"?
- 4L Access Controlled Greenfield Highway section on NH-163G Khammam Vijayawada from V. Venkatayapalem village at Design Ch. 220.480 Km to BrahmanapalliK village at Design Ch. 250.400 Km Package-I. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹973 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹973 Cr and has been revised to ₹1022 Cr — a cost overrun of +5%. Expenditure to date: ₹272 Cr (26.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Access Controlled Greenfield Highway section on NH-163G K is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618817. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Access Controlled Greenfield Highway section on NH-163G K is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.