Original Cost
₹2541 Cr
Baseline estimate
Revised Cost
₹1983 Cr
Latest approved cost
Expenditure
₹199 Cr
Spent to date
Utilization
10.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1784 Cr
Budget left
Spent
₹199 Cr
Remaining
₹1784 Cr
Total
₹1983 Cr
Project Approved
Construction / Implementation
Original End Date
27/09/2027
Revised Completion
27/09/2027
Completed
Project is within original budget of ₹2541 Cr — no cost escalation recorded.
Expenditure stands at ₹199 Cr, which is 10.0% of the revised project cost.
Remaining budget: ₹1784 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.