Roads & HighwaysIPM · Central Project#618568

4/6L Southern Ayodhya Bypass from Km 5.000 to Km 37.172 starting near Km. 112.540 and ending at Km. 153.281 of NH-27

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹1983 CrUtilization: 16.5%

Original Cost

₹2541 Cr

Baseline estimate

On budget

Revised Cost

₹1983 Cr

Latest approved cost

Expenditure

₹327 Cr

Spent to date

Utilization

16.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1656 Cr

Budget left

Budget Utilization

16.5%
0%25%50%75%100%

Spent

₹327 Cr

Remaining

₹1656 Cr

Total

₹1983 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/09/2027

Revised Completion

27/09/2027

Completed

Project Details

Project Code618568
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹2541 Cr
Revised Cost₹1983 Cr
Expenditure₹327 Cr
Original End Date27/09/2027
Revised Date27/09/2027

Project Intelligence

Project is within original budget of ₹2541 Cr — no cost escalation recorded.

Expenditure stands at ₹327 Cr, which is 16.5% of the revised project cost.

Remaining budget: ₹1656 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4/6L Southern Ayodhya Bypass from Km 5.000 to Km 37.172 starting near Km. 112.540 and ending at Km. 153.281 of NH-27 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2541.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4/6L Southern Ayodhya Bypass from Km 5.000 to Km 37.172 starting near Km. 112.54"?
4/6L Southern Ayodhya Bypass from Km 5.000 to Km 37.172 starting near Km. 112.540 and ending at Km. 153.281 of NH-27 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹2541 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2541 Cr and has been revised to ₹1983 Cr — a cost overrun of -22%. Expenditure to date: ₹327 Cr (16.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4/6L Southern Ayodhya Bypass from Km 5.000 to Km 37.172 star is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618568. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4/6L Southern Ayodhya Bypass from Km 5.000 to Km 37.172 star is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.