Roads & HighwaysIPM · Central Project#618567

4/6L of Northern Ayodhya Bypass starting Km. 112.540 and ending Km. 139.928 north of existing NH-27 part-1 and part-2 south of NH-27 from km 0.000 to km 5.000.

Ministry of Road Transport & HighwaysUttar Pradesh
Revised Cost: ₹1834 CrUtilization: 15.6%

Original Cost

₹2289 Cr

Baseline estimate

On budget

Revised Cost

₹1834 Cr

Latest approved cost

Expenditure

₹286 Cr

Spent to date

Utilization

15.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹1548 Cr

Budget left

Budget Utilization

15.6%
0%25%50%75%100%

Spent

₹286 Cr

Remaining

₹1548 Cr

Total

₹1834 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/01/2028

Revised Completion

07/01/2028

Completed

Project Details

Project Code618567
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttar Pradesh
Data Month2026-08

Financial Summary

Original Cost₹2289 Cr
Revised Cost₹1834 Cr
Expenditure₹286 Cr
Original End Date06/01/2028
Revised Date07/01/2028

Project Intelligence

Project is within original budget of ₹2289 Cr — no cost escalation recorded.

Expenditure stands at ₹286 Cr, which is 15.6% of the revised project cost.

Remaining budget: ₹1548 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4/6L of Northern Ayodhya Bypass starting Km. 112.540 and ending Km. 139.928 north of existing NH-27 part-1 and part-2 south of NH-27 from km 0.000 to km 5.000. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2289.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4/6L of Northern Ayodhya Bypass starting Km. 112.540 and ending Km. 139.928 nort"?
4/6L of Northern Ayodhya Bypass starting Km. 112.540 and ending Km. 139.928 north of existing NH-27 part-1 and part-2 south of NH-27 from km 0.000 to km 5.000. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹2289 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2289 Cr and has been revised to ₹1834 Cr — a cost overrun of -19.9%. Expenditure to date: ₹286 Cr (15.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4/6L of Northern Ayodhya Bypass starting Km. 112.540 and end is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618567. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4/6L of Northern Ayodhya Bypass starting Km. 112.540 and end is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.