4/6 Laning of Raipur-Simga Pkg-I from km. 0.00 to km. 48.58
Original Cost
₹1097 Cr
Baseline estimate
Revised Cost
₹1172 Cr
Latest approved cost
Expenditure
₹906 Cr
Spent to date
Utilization
77.2%
Of revised budget
Cost Status
+6.9%
+₹75 Cr increase
Remaining
₹267 Cr
Budget left
Budget Utilization
77.2%Spent
₹906 Cr
Remaining
₹267 Cr
Total
₹1172 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1097 Cr
Revised Cost
₹1172 Cr
Increase
+₹75 Cr
Escalation
+6.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/04/2018
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹75 Cr (6.9%) from the original estimate of ₹1097 Cr.
Expenditure stands at ₹906 Cr, which is 77.2% of the revised project cost.
Remaining budget: ₹267 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4/6 Laning of Raipur-Simga Pkg-I from km. 0.00 to km. 48.58 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1097.00 Cr, later revised to ₹1172.36 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4/6 Laning of Raipur-Simga Pkg-I from km. 0.00 to km. 48.58"?
- 4/6 Laning of Raipur-Simga Pkg-I from km. 0.00 to km. 48.58 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Chhattisgarh. Original cost: ₹1097 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1097 Cr and has been revised to ₹1172 Cr — a cost overrun of +6.9%. Expenditure to date: ₹906 Cr (77.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4/6 Laning of Raipur-Simga Pkg-I from km. 0.00 to km. 48.58 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619103. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4/6 Laning of Raipur-Simga Pkg-I from km. 0.00 to km. 48.58 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.