Original Cost
₹1097 Cr
Baseline estimate
Revised Cost
₹1172 Cr
Latest approved cost
Expenditure
₹106 Cr
Spent to date
Utilization
9.0%
Of revised budget
Cost Status
+6.9%
+₹75 Cr increase
Remaining
₹1066 Cr
Budget left
Spent
₹106 Cr
Remaining
₹1066 Cr
Total
₹1172 Cr
Original Cost
₹1097 Cr
Revised Cost
₹1172 Cr
Increase
+₹75 Cr
Escalation
+6.9%
Project Approved
Construction / Implementation
Original End Date
20/04/2018
Revised Completion
30/06/2026
Completed
Cost has increased by ₹75 Cr (6.9%) from the original estimate of ₹1097 Cr.
Expenditure stands at ₹106 Cr, which is 9.0% of the revised project cost.
Remaining budget: ₹1066 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.