Roads & HighwaysIPM · Central Project#618316

4-Laning of Vairengte - Chhimluang section Package-3 of NH-306 from Existing Chainage km 43000 to Km 59700 Design Chainage km 46000 to km 60850 on Silchar - Vairengte- Sairang road in the State of Mizoram under Bharatmala Pariyojna under NHO-NE. Package-1&2 in Assam state

Ministry of Road Transport & HighwaysMizoram
Revised Cost: ₹491 CrUtilization: 49.9%

Original Cost

₹491 Cr

Baseline estimate

On budget

Revised Cost

₹491 Cr

Latest approved cost

Expenditure

₹245 Cr

Spent to date

Utilization

49.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹246 Cr

Budget left

Budget Utilization

49.9%
0%25%50%75%100%

Spent

₹245 Cr

Remaining

₹246 Cr

Total

₹491 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/01/2027

Revised Completion

30/12/2026

Completed

Project Details

Project Code618316
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMizoram
Data Month2026-08

Financial Summary

Original Cost₹491 Cr
Revised Cost₹491 Cr
Expenditure₹245 Cr
Original End Date07/01/2027
Revised Date30/12/2026

Project Intelligence

Project is within original budget of ₹491 Cr — no cost escalation recorded.

Expenditure stands at ₹245 Cr, which is 49.9% of the revised project cost.

Remaining budget: ₹246 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4-Laning of Vairengte - Chhimluang section Package-3 of NH-306 from Existing Chainage km 43000 to Km 59700 Design Chainage km 46000 to km 60850 on Silchar - Vairengte- Sairang road in the State of Mizoram under Bharatmala Pariyojna under NHO-NE. Package-1&2 in Assam state is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹491.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4-Laning of Vairengte - Chhimluang section Package-3 of NH-306 from Existing Ch"?
4-Laning of Vairengte - Chhimluang section Package-3 of NH-306 from Existing Chainage km 43000 to Km 59700 Design Chainage km 46000 to km 60850 on Silchar - Vairengte- Sairang road in the State of Mizoram under Bharatmala Pariyojna under NHO-NE. Package-1&2 in Assam state is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Mizoram. Original cost: ₹491 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹491 Cr has not been significantly revised. Expenditure: ₹245 Cr (49.9% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4-Laning of Vairengte - Chhimluang section Package-3 of NH- is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618316. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4-Laning of Vairengte - Chhimluang section Package-3 of NH- is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.