Original Cost
₹596 Cr
Baseline estimate
Revised Cost
₹596 Cr
Latest approved cost
Expenditure
₹21 Cr
Spent to date
Utilization
3.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹575 Cr
Budget left
Spent
₹21 Cr
Remaining
₹575 Cr
Total
₹596 Cr
Project Approved
Construction / Implementation
Original End Date
07/01/2027
Revised Completion
30/12/2026
Completed
Project is within original budget of ₹596 Cr — no cost escalation recorded.
Expenditure stands at ₹21 Cr, which is 3.5% of the revised project cost.
Remaining budget: ₹575 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.