Original Cost
₹1471 Cr
Baseline estimate
Revised Cost
₹1471 Cr
Latest approved cost
Expenditure
₹408 Cr
Spent to date
Utilization
27.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1064 Cr
Budget left
Spent
₹408 Cr
Remaining
₹1064 Cr
Total
₹1471 Cr
Project Approved
Construction / Implementation
Original End Date
13/03/2026
Revised Completion
25/01/2027
Completed
Project is within original budget of ₹1471 Cr — no cost escalation recorded.
Expenditure stands at ₹408 Cr, which is 27.7% of the revised project cost.
Remaining budget: ₹1064 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.