Roads & HighwaysIPM · Central Project#618783

4-laning of Pilibhit - Sitarganj from Km. 32.500 to Km. 70.800 Pkg-2 of NH-30

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹1471 CrUtilization: 32.7%

Original Cost

₹1471 Cr

Baseline estimate

On budget

Revised Cost

₹1471 Cr

Latest approved cost

Expenditure

₹481 Cr

Spent to date

Utilization

32.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹991 Cr

Budget left

Budget Utilization

32.7%
0%25%50%75%100%

Spent

₹481 Cr

Remaining

₹991 Cr

Total

₹1471 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

13/03/2026

Revised Completion

31/10/2027

Completed

Project Details

Project Code618783
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹1471 Cr
Revised Cost₹1471 Cr
Expenditure₹481 Cr
Original End Date13/03/2026
Revised Date31/10/2027

Project Intelligence

Project is within original budget of ₹1471 Cr — no cost escalation recorded.

Expenditure stands at ₹481 Cr, which is 32.7% of the revised project cost.

Remaining budget: ₹991 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4-laning of Pilibhit - Sitarganj from Km. 32.500 to Km. 70.800 Pkg-2 of NH-30 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1471.00 Cr, later revised to ₹1471.19 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4-laning of Pilibhit - Sitarganj from Km. 32.500 to Km. 70.800 Pkg-2 of NH-30"?
4-laning of Pilibhit - Sitarganj from Km. 32.500 to Km. 70.800 Pkg-2 of NH-30 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹1471 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1471 Cr has not been significantly revised. Expenditure: ₹481 Cr (32.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4-laning of Pilibhit - Sitarganj from Km. 32.500 to Km. 70.8 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618783. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4-laning of Pilibhit - Sitarganj from Km. 32.500 to Km. 70.8 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.