Original Cost
₹1002 Cr
Baseline estimate
Revised Cost
₹1304 Cr
Latest approved cost
Expenditure
₹781 Cr
Spent to date
Utilization
59.9%
Of revised budget
Cost Status
+30.2%
+₹302 Cr increase
Remaining
₹523 Cr
Budget left
Spent
₹781 Cr
Remaining
₹523 Cr
Total
₹1304 Cr
Original Cost
₹1002 Cr
Revised Cost
₹1304 Cr
Increase
+₹302 Cr
Escalation
+30.2%
Project Approved
Construction / Implementation
Original End Date
05/01/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹302 Cr (30.2%) from the original estimate of ₹1002 Cr.
Expenditure stands at ₹781 Cr, which is 59.9% of the revised project cost.
Remaining budget: ₹523 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.