Original Cost
₹563 Cr
Baseline estimate
Revised Cost
₹795 Cr
Latest approved cost
Expenditure
₹120 Cr
Spent to date
Utilization
15.1%
Of revised budget
Cost Status
+41.2%
+₹232 Cr increase
Remaining
₹675 Cr
Budget left
Spent
₹120 Cr
Remaining
₹675 Cr
Total
₹795 Cr
Original Cost
₹563 Cr
Revised Cost
₹795 Cr
Increase
+₹232 Cr
Escalation
+41.2%
Project Approved
Construction / Implementation
Original End Date
28/09/2025
Revised Completion
Completed
Cost has increased by ₹232 Cr (41.2%) from the original estimate of ₹563 Cr.
Expenditure stands at ₹120 Cr, which is 15.1% of the revised project cost.
Remaining budget: ₹675 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.