4 laning of Aligarh-Palwal Section from Km. 46.390 Design Chainage to Km. 69.110 Terminating at junction EPE Package-II from Kurana- Eastern Peripheral Expressway of NH-334D
Original Cost
₹939 Cr
Baseline estimate
Revised Cost
₹904 Cr
Latest approved cost
Expenditure
₹277 Cr
Spent to date
Utilization
30.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹627 Cr
Budget left
Budget Utilization
30.6%Spent
₹277 Cr
Remaining
₹627 Cr
Total
₹904 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
26/08/2027
Revised Completion
27/08/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹939 Cr — no cost escalation recorded.
Expenditure stands at ₹277 Cr, which is 30.6% of the revised project cost.
Remaining budget: ₹627 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4 laning of Aligarh-Palwal Section from Km. 46.390 Design Chainage to Km. 69.110 Terminating at junction EPE Package-II from Kurana- Eastern Peripheral Expressway of NH-334D is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹939.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4 laning of Aligarh-Palwal Section from Km. 46.390 Design Chainage to Km. 69.110"?
- 4 laning of Aligarh-Palwal Section from Km. 46.390 Design Chainage to Km. 69.110 Terminating at junction EPE Package-II from Kurana- Eastern Peripheral Expressway of NH-334D is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹939 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹939 Cr and has been revised to ₹904 Cr — a cost overrun of -3.7%. Expenditure to date: ₹277 Cr (30.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4 laning of Aligarh-Palwal Section from Km. 46.390 Design Ch is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618691. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4 laning of Aligarh-Palwal Section from Km. 46.390 Design Ch is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.