km. 0.00 to km. 63.655
Original Cost
₹638 Cr
Baseline estimate
Revised Cost
₹1068 Cr
Latest approved cost
Expenditure
₹623 Cr
Spent to date
Utilization
58.3%
Of revised cost
Cost Overrun
+67.3%
+₹430 Cr
Remaining
₹445 Cr
Budget left
Spent
₹623 Cr
Remaining
₹445 Cr
Total
₹1068 Cr
58.3%
Utilized
Original Cost
₹638 Cr
Revised Cost
₹1068 Cr
Increase
+₹430 Cr
Escalation
+67.3%
Project Approved
Construction / Implementation
Original End Date
2021-11-04
Revised Completion
2026-05-31
Completed
Cost has increased by ₹430 Cr (67.3%) from the original estimate of ₹638 Cr.
Expenditure stands at ₹623 Cr, which is 58.3% of the revised project cost.
Remaining budget: ₹445 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.