Roads & HighwaysIPM · Central Project +2.1% overrun#618890

2L PS of Hamirpur Bypass from Km 121.175 to Km.138.295 of NH-103&3

Ministry of Road Transport & HighwaysHimachal Pradesh
Revised Cost: ₹755 CrUtilization: 49.0%Overrun: +₹16 Cr

Original Cost

₹739 Cr

Baseline estimate

+2% overrun

Revised Cost

₹755 Cr

Latest approved cost

Expenditure

₹370 Cr

Spent to date

Utilization

49.0%

Of revised budget

Escalated

Cost Status

+2.1%

+₹16 Cr increase

Remaining

₹385 Cr

Budget left

Budget Utilization

49.0%
0%25%50%75%100%

Spent

₹370 Cr

Remaining

₹385 Cr

Total

₹755 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹739 Cr

Revised Cost

₹755 Cr

Increase

+₹16 Cr

Escalation

+2.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/10/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code618890
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHimachal Pradesh
Data Month2026-08

Financial Summary

Original Cost₹739 Cr
Revised Cost₹755 Cr
Expenditure₹370 Cr
Original End Date28/10/2025
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹16 Cr (2.1%) from the original estimate of ₹739 Cr.

Expenditure stands at ₹370 Cr, which is 49.0% of the revised project cost.

Remaining budget: ₹385 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

2L PS of Hamirpur Bypass from Km 121.175 to Km.138.295 of NH-103&3 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹739.00 Cr, later revised to ₹754.82 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "2L PS of Hamirpur Bypass from Km 121.175 to Km.138.295 of NH-103&3"?
2L PS of Hamirpur Bypass from Km 121.175 to Km.138.295 of NH-103&3 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Himachal Pradesh. Original cost: ₹739 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹739 Cr and has been revised to ₹755 Cr — a cost overrun of +2.1%. Expenditure to date: ₹370 Cr (49.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
2L PS of Hamirpur Bypass from Km 121.175 to Km.138.295 of NH is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618890. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 2L PS of Hamirpur Bypass from Km 121.175 to Km.138.295 of NH is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.