Original Cost
₹739 Cr
Baseline estimate
Revised Cost
₹755 Cr
Latest approved cost
Expenditure
₹233 Cr
Spent to date
Utilization
30.9%
Of revised budget
Cost Status
+2.1%
+₹16 Cr increase
Remaining
₹521 Cr
Budget left
Spent
₹233 Cr
Remaining
₹521 Cr
Total
₹755 Cr
Original Cost
₹739 Cr
Revised Cost
₹755 Cr
Increase
+₹16 Cr
Escalation
+2.1%
Project Approved
Construction / Implementation
Original End Date
28/10/2025
Revised Completion
30/09/2026
Completed
Cost has increased by ₹16 Cr (2.1%) from the original estimate of ₹739 Cr.
Expenditure stands at ₹233 Cr, which is 30.9% of the revised project cost.
Remaining budget: ₹521 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.