Environmental ClearanceForest Clearance

Protected forest land admeasuring 2.0264 Ha is required for Construction of Luv Kush Eco-Tourism park at Valmiki Nagar, Dist West Champaran Bihar

Pashchim Champaran, BiharBihar State tourism Deve-lopment Corporation Ltd
Proposal no.FP/BR/OTHERS/540019/2025

Current status

Pending at DFO due to EDS by Nodal Officer
  1. SubmittedApplication filed on PARIVESH
  2. VerificationChecked for completeness
  3. 3ExaminationNowScrutiny; shortfalls raised as EDS
  4. 4Expert appraisalAppraised by the expert committee (SEAC/EAC)
  5. 5DecisionClearance granted or refused

Updated 6 Oct 2026

Project cost
₹51.54 Cr
As filed on PARIVESH
Land required
2.03 Ha
Total project area
Submitted
10 Feb 2026
Filed on PARIVESH
Documents
2
PDF & KML files

About this proposal

Overview

Protected forest land admeasuring 2.0264 Ha is required for Construction of Luv Kush Eco-Tourism park at Valmiki Nagar, Dist West Champaran Bihar is a Forest Clearance (FC) proposal filed under India's PARIVESH portal, tracked here as part of BiharInfraTales' Bihar clearance monitoring dashboard. The proposal (reference number FP/BR/OTHERS/540019/2025) was submitted by Rajani Kant Tiwary on behalf of Bihar State tourism Deve-lopment Corporation Ltd in Pashchim Champaran, Bihar, with an estimated project cost of ₹51.54 crore spread over 2.03 hectares.

The proposal falls under the Forestry / Linear sector and currently carries the status "Pending at DFO due to EDS by Nodal Officer". Forest Clearance is required under the Forest (Conservation) Act for diversion of forest land for non-forest infrastructure and development purposes, governed by the Ministry of Environment, Forest and Climate Change (MoEFCC) and state forest departments.

The application was submitted on 2026-02-10. The land requirement comprises 2.0264 ha of forest land and 0 ha of non-forest land. Stage-I approval on 17-SEP-2026. Full proposal documents, boundary (KML) data, and the exact project location, where published by PARIVESH, are linked on this page. This record is updated as the clearance moves through verification, appraisal, and the final grant or rejection stage.

PARIVESH data

Proposal record

12 fields
Proposal Number
FP/BR/OTHERS/540019/2025
Organisation
Bihar State tourism Deve-lopment Corporation Ltd
Applicant
Rajani Kant Tiwary
Clearance Type
Forest Clearance
Proposal Type
FC
Current Status
Pending at DFO due to EDS by Nodal Officer
Submission Date
2026-02-10
Stage-I Approval Date
17-SEP-2026
Nodal Accepted Date
07-APR-2026
Shape of Project
Non - Linear
Forest Land
2.0264 Ha
Non-Forest Land
0 Ha

Where

Project location

3 fields
District
Pashchim Champaran
State
Bihar
Total Land Area
2.03 Ha

Source files

Documents & boundary data

2 files

Data from the Government of India's PARIVESH environmental clearance portal.

Questions

Frequently asked questions

1What is the Environmental Clearance status of "Protected forest land admeasuring 2.0264 Ha is required for Construction of Luv "?

As per the latest PARIVESH data, proposal FP/BR/OTHERS/540019/2025 carries the status "Pending at DFO due to EDS by Nodal Officer". It is a infrastructure-sector project in Pashchim Champaran, Bihar.

2Who is the applicant for this Environmental Clearance proposal?

The proposal was filed by Rajani Kant Tiwary on behalf of Bihar State tourism Deve-lopment Corporation Ltd. The clearance type is Forest Clearance and it is tracked under PARIVESH reference FP/BR/OTHERS/540019/2025.

3What is the project cost and land requirement?

The proposal reports an estimated cost of ₹51.54 Cr and requires 2.03 Ha of land (2.0264 ha forest, 0 ha non-forest).

4What is Environmental Clearance (EC) and why does this project need it?

Environmental Clearance is a mandatory approval under India's Environment Impact Assessment (EIA) framework, granted by the MoEFCC or the State Environment Impact Assessment Authority (SEIAA) via the PARIVESH portal. Projects that can significantly affect the environment must obtain EC — covering appraisal of pollution, land use, and ecological impact — before construction or expansion can lawfully begin.