Nalanda·Nalanda·Bihar
Admin Approval
₹6613 L
Agreement Amount
₹39.72 Cr
Commencement
02 May 2023
Scheduled Completion
01 May 2025
1.) Pile work 88/88 Completed. 2.) Pile Cap 19/20 Completed. 3.) Abutment/ Pier Shaft-18/20 No. Completed. 4.) Hammer head 18/20 Nos. Completed. 5.) Girder 32/74 & Slab 8/19 Completed. 5.) Land Acquisition work in Progress.